Project Description
This project will provide a new park & ride lot at Exit 107 off Interstate 64. The new lot will provide 25 parking spaces and include a transit bus turnaround, a transit shelter, a bicycle rack, and turn lane improvements.
Cost Estimate
Preliminary Engineering ....................................$0.9 million
Right of Way Acquisition ....................................$0.2 million
Construction .............................................$1.6 million
Needs Addressed
![User_icon User_icon](https://campo.tjpdc.org/wp-content/uploads/user_icon.png)
Transportation
Demand Management
![Cycle Bicycle Access](https://campo.tjpdc.org/wp-content/uploads/cycle.png)
Bicycle Access
Outstanding Concerns
No known concerns at this time
Entity Submitting
TJPDC
![Smartscale smartscale](https://campo.tjpdc.org/wp-content/uploads/smartscale-1.png)