Project Description
This project will leverage existing Transportation Alternatives funding to complete a shared use path that connects a commercial space adjacent to 5th Street to the Fifth Street Station shopping center. This trail is the first of a planned network of trails in the area to connect bicyclists and pedestrians to commercial and recreational amenities.
Cost Estimate
Preliminary Engineering ....................................$1.0 million
Right of Way Acquisition ....................................$1.0 million
Construction .............................................$4.0 million
Needs Addressed
![Ped_access Ped_access](https://campo.tjpdc.org/wp-content/uploads/ped_access.png)
Pedestrian Access
![Cycle Bicycle Access](https://campo.tjpdc.org/wp-content/uploads/cycle.png)
Bicycle Access
Outstanding Concerns
Potential interruptions to current use of trails in the area
Entity Submitting
TJPDC